Anonymous project

How a New Router Factory Automated 10 THT Component Types and Increased Insertion Efficiency by 4×

An anonymized project showing how a new router factory moved ten THT component types from manual to automated insertion.

Two odd-form insertion machines with multiple bowl feeders in an anonymized router factory

Confirmed equipment

  • 2 Odd Form Insertion Machines
  • 8 bowl feeders
  • 1 tube feeder
  • 2 tape feeders

Leon’s role

  • Requirement clarification
  • Solution coordination
  • Sample testing
  • Commercial follow-up
  • Installation, training and after-sales coordination

Confirmed outcome

Approximately four times the previous insertion production efficiency for this project.

This is a project-specific result, not a universal performance guarantee. A comparable outcome depends on current component, PCB, feeding and engineering evidence.

Starting from an empty factory

The customer was establishing a new router-manufacturing facility in Russia without existing insertion equipment. The immediate engineering task was to move ten electronic component types from manual insertion to an automated process, including multi-pin router ports.

The insertion and feeding configuration

The delivered core solution consisted of two odd-form insertion machines. Component presentation was handled by eight bowl feeders, one tube feeder and two tape feeders. Conveyors, board loaders, board unloaders and a complete production line were not part of this project scope.

Leon’s role in the project

Leon coordinated the project from initial requirement clarification through PCB and component information collection, solution coordination, sample testing, commercial follow-up, installation and training coordination, and after-sales follow-up.

Confirmed project outcome

For this installation, the customer achieved approximately four times the previous insertion production efficiency. This is a project-specific reported result; actual outcomes for other factories depend on component mix, PCB design, feeding method, takt requirements and engineering validation.

Two odd-form insertion machines and multiple bowl feeders operating in an anonymized router factory

Information needed for a similar evaluation

Prepare PCB files or photos, component photos and packaging formats, a component list, the current insertion method, required capacity, available floor space and representative samples for engineering review.

Project context

Engineering-led coordination

Professional profile

Leon Hong

SMT/THT Automation Sales Engineer

Shenzhen, China

Current affiliation: SMT/THT Automation Sales Engineer at Southern Machinery

Engineering-led international B2B work for SMT, THT and PCB assembly automation projects.